單項(xiàng)選擇題

The inputs of developing project management plan do not include()

A.project charter
B.stakeholder management strategy
C.project scope statement
D.outputs from planning processes


你可能感興趣的試題

1.單項(xiàng)選擇題

Which of the following statement related to PMO is not correct?()

A.The specific form, function, and structure of a PMO are dependent upon the needs of the organization that it supports.
B.One of the key features of a PMO is managing shared resources across all projects administered by the PMO.
C.The PMO focuses on the specified project objectives.
D.The PMO optimizes the use of shared organizational resources across all projects.

最新試題

Project () Management includes the processes required to ensure that the project includes all the work required, and only the work required, to complete the project successfully.

題型:單項(xiàng)選擇題

The() defines the phases that connect the beginning of a project to its end.

題型:單項(xiàng)選擇題

空白(2)處應(yīng)選擇()

題型:單項(xiàng)選擇題

The () describes, in detail, the project's deliverables and the work required to create those deliverables.

題型:單項(xiàng)選擇題

()from one phase are usually reviewed for completeness and accuracy and approved before work starts on the next phase.

題型:單項(xiàng)選擇題

Which of the following statement related to PMO is not correct?()

題型:單項(xiàng)選擇題

PDM includes four types of dependencies or precedence relationships: (). The completion of the successor activity depends upon the initiation of the predecessor activity.

題型:單項(xiàng)選擇題

()means that every project has a definite beginning and a definite end.

題型:單項(xiàng)選擇題

The process of()schedule activity durations uses information on schedule activity scope of work, required resource types, estimated resource quantities, and resource calendars with resource availabilities.

題型:單項(xiàng)選擇題

Organizations perform work to achieve a set of objectives. Generally, work can be categorized as either projects or operations, although the two sometimes are()

題型:單項(xiàng)選擇題