單項選擇題

()is the budgeted amount for the work actually completed on the schedule activity or WBS component during a given time period.

A.Planned value
B.Earned value
C.Actual cost
D.Cost variance


你可能感興趣的試題

3.單項選擇題

The () describes, in detail, the project's deliverables and the work required to create those deliverables.

A.project scope statement
B.project requirement
C.project charter
D.product specification

4.單項選擇題The()provides the project manager with the authority to apply organizational resources to project activities.

A.project management plan
B.contract
C.project human resource plan
D.project charter

7.單項選擇題

The() defines the phases that connect the beginning of a project to its end.

A.schedule
B.project life cycle
C.temporary
D.milestone

8.單項選擇題

()means that every project has a definite beginning and a definite end.

A.Project phase
B.Unique
C.Temporary
D.Closure

9.單項選擇題

() is one of the quality planning outputs.

A.Scope base line
B.Cost of quality
C.Product specification
D.Quality checklist

10.單項選擇題

The inputs of developing project management plan do not include()

A.project charter
B.stakeholder management strategy
C.project scope statement
D.outputs from planning processes

最新試題

The()process analyzes the effect of risk events and assigns a numerical rating to those risks.

題型:單項選擇題

PDM includes four types of dependencies or precedence relationships: (). The completion of the successor activity depends upon the initiation of the predecessor activity.

題型:單項選擇題

() are individuals and organizations that are actively involved in the project, or whose interests may be affected as a result of project execution or project completion.

題型:單項選擇題

空白(2)處應選擇()

題型:單項選擇題

()is the budgeted amount for the work actually completed on the schedule activity or WBS component during a given time period.

題型:單項選擇題

The()provides the project manager with the authority to apply organizational resources to project activities.

題型:單項選擇題

()from one phase are usually reviewed for completeness and accuracy and approved before work starts on the next phase.

題型:單項選擇題

The process of()schedule activity durations uses information on schedule activity scope of work, required resource types, estimated resource quantities, and resource calendars with resource availabilities.

題型:單項選擇題

()is a category assigned to products or services having the same functional use but different technical characteristics. It is not same as quality.

題型:單項選擇題

Project() Management is the Knowledge Area that employs the processes required to ensure timely and appropriate generation, collection, distribution, storage, retrieval, and ultimate disposition of project information.

題型:單項選擇題