()is the budgeted amount for the work actually completed on the schedule activity or WBS component during a given time period.
A.Planned value
B.Earned value
C.Actual cost
D.Cost variance
您可能感興趣的試卷
你可能感興趣的試題
PDM includes four types of dependencies or precedence relationships: (). The completion of the successor activity depends upon the initiation of the predecessor activity.
A.Finish-to-Start
B.Finish-to-Finish
C.Start-to-Start
D.Start-to-Finish
The process of()schedule activity durations uses information on schedule activity scope of work, required resource types, estimated resource quantities, and resource calendars with resource availabilities.
A.estimating
B.defining
C.planning
D.sequencing
The () describes, in detail, the project's deliverables and the work required to create those deliverables.
A.project scope statement
B.project requirement
C.project charter
D.product specification
A.project management plan
B.contract
C.project human resource plan
D.project charter
The ()Process Group consists of the processes used to complete the work defined in the project management plan to accomplish the project's requirements.
A.Planning
B.Executing
C.Monitoring and Controlling
D.Closing
() are individuals and organizations that are actively involved in the project, or whose interests may be affected as a result of project execution or project completion.
A.Project managers
B.Project team members
C.Sponsors
D.Project stakeholders
The() defines the phases that connect the beginning of a project to its end.
A.schedule
B.project life cycle
C.temporary
D.milestone
()means that every project has a definite beginning and a definite end.
A.Project phase
B.Unique
C.Temporary
D.Closure
() is one of the quality planning outputs.
A.Scope base line
B.Cost of quality
C.Product specification
D.Quality checklist
The inputs of developing project management plan do not include()
A.project charter
B.stakeholder management strategy
C.project scope statement
D.outputs from planning processes
最新試題
The()process analyzes the effect of risk events and assigns a numerical rating to those risks.
PDM includes four types of dependencies or precedence relationships: (). The completion of the successor activity depends upon the initiation of the predecessor activity.
() are individuals and organizations that are actively involved in the project, or whose interests may be affected as a result of project execution or project completion.
空白(2)處應選擇()
()is the budgeted amount for the work actually completed on the schedule activity or WBS component during a given time period.
The()provides the project manager with the authority to apply organizational resources to project activities.
()from one phase are usually reviewed for completeness and accuracy and approved before work starts on the next phase.
The process of()schedule activity durations uses information on schedule activity scope of work, required resource types, estimated resource quantities, and resource calendars with resource availabilities.
()is a category assigned to products or services having the same functional use but different technical characteristics. It is not same as quality.
Project() Management is the Knowledge Area that employs the processes required to ensure timely and appropriate generation, collection, distribution, storage, retrieval, and ultimate disposition of project information.