In the project management context,() includes characteristics of unification, consolidation, articulation, and integrative actions that are crucial to project completion, successfully meeting customer and other stakeholder requirements, and managing expectations.
A.Integration
B.Scope
C.Configuration
D.Requirement
您可能感興趣的試卷
你可能感興趣的試題
Organizations perform work to achieve a set of objectives. Generally, work can be categorized as either projects or operations, although the two sometimes are()
A.confused
B.same
C.overlap
D.dissever
()from one phase are usually reviewed for completeness and accuracy and approved before work starts on the next phase.
A.Process
B.Milestone
C.Work
D.Deliverables
()involves comparing actual or planned project practices to those of other projects to generate ideas for improvement and to provide a basis by which to measure performance. These other projects can be within the performing organization or outside of it, and can be within the same or in another application area.
A.Metrics
B.Measurement
C.Benchmarking
D.Baseline
()is the budgeted amount for the work actually completed on the schedule activity or WBS component during a given time period.
A.Planned value
B.Earned value
C.Actual cost
D.Cost variance
PDM includes four types of dependencies or precedence relationships: (). The completion of the successor activity depends upon the initiation of the predecessor activity.
A.Finish-to-Start
B.Finish-to-Finish
C.Start-to-Start
D.Start-to-Finish
The process of()schedule activity durations uses information on schedule activity scope of work, required resource types, estimated resource quantities, and resource calendars with resource availabilities.
A.estimating
B.defining
C.planning
D.sequencing
The () describes, in detail, the project's deliverables and the work required to create those deliverables.
A.project scope statement
B.project requirement
C.project charter
D.product specification
A.project management plan
B.contract
C.project human resource plan
D.project charter
The ()Process Group consists of the processes used to complete the work defined in the project management plan to accomplish the project's requirements.
A.Planning
B.Executing
C.Monitoring and Controlling
D.Closing
() are individuals and organizations that are actively involved in the project, or whose interests may be affected as a result of project execution or project completion.
A.Project managers
B.Project team members
C.Sponsors
D.Project stakeholders
最新試題
The ()Process Group consists of the processes used to complete the work defined in the project management plan to accomplish the project's requirements.
()means that every project has a definite beginning and a definite end.
PDM includes four types of dependencies or precedence relationships: (). The completion of the successor activity depends upon the initiation of the predecessor activity.
In the project management context,() includes characteristics of unification, consolidation, articulation, and integrative actions that are crucial to project completion, successfully meeting customer and other stakeholder requirements, and managing expectations.
Which of the following statement related to PMO is not correct?()
The()provides the project manager with the authority to apply organizational resources to project activities.
() is one of the quality planning outputs.
The () describes, in detail, the project's deliverables and the work required to create those deliverables.
Organizations perform work to achieve a set of objectives. Generally, work can be categorized as either projects or operations, although the two sometimes are()
()involves comparing actual or planned project practices to those of other projects to generate ideas for improvement and to provide a basis by which to measure performance. These other projects can be within the performing organization or outside of it, and can be within the same or in another application area.