Project Quality Management must address the management of the project and the() of the project. While Project Quality Management applies to all projects, regardless of the nature of their product, product quality measures and techniques are specific to the particular type of product produced by the project.
A.performance
B.process
C.product
D.object
您可能感興趣的試卷
你可能感興趣的試題
In approximating costs, the estimator considers the possible causes of variation of the cost estimates, including() .
A.budget
B.plan
C.risk
D.contract
On some projects, especially ones of smaller scope, activity sequencing, activity resource estimating, activity duration estimating, and () are so tightly linked that they are viewed as a single process that can be performed by a person over a relatively short period of time.
A.time estimating
B.cost estimating
C.project planning
D.schedule development
Project () Management includes the processes required to ensure that the project includes all the work required, and only the work required, to complete the project successfully.
A.Integration
B.Scope
C.Configuration
D.Requirement
In the project management context,() includes characteristics of unification, consolidation, articulation, and integrative actions that are crucial to project completion, successfully meeting customer and other stakeholder requirements, and managing expectations.
A.Integration
B.Scope
C.Configuration
D.Requirement
Organizations perform work to achieve a set of objectives. Generally, work can be categorized as either projects or operations, although the two sometimes are()
A.confused
B.same
C.overlap
D.dissever
()from one phase are usually reviewed for completeness and accuracy and approved before work starts on the next phase.
A.Process
B.Milestone
C.Work
D.Deliverables
()involves comparing actual or planned project practices to those of other projects to generate ideas for improvement and to provide a basis by which to measure performance. These other projects can be within the performing organization or outside of it, and can be within the same or in another application area.
A.Metrics
B.Measurement
C.Benchmarking
D.Baseline
()is the budgeted amount for the work actually completed on the schedule activity or WBS component during a given time period.
A.Planned value
B.Earned value
C.Actual cost
D.Cost variance
PDM includes four types of dependencies or precedence relationships: (). The completion of the successor activity depends upon the initiation of the predecessor activity.
A.Finish-to-Start
B.Finish-to-Finish
C.Start-to-Start
D.Start-to-Finish
The process of()schedule activity durations uses information on schedule activity scope of work, required resource types, estimated resource quantities, and resource calendars with resource availabilities.
A.estimating
B.defining
C.planning
D.sequencing
最新試題
()involves comparing actual or planned project practices to those of other projects to generate ideas for improvement and to provide a basis by which to measure performance. These other projects can be within the performing organization or outside of it, and can be within the same or in another application area.
空白(2)處應(yīng)選擇()
The inputs of developing project management plan do not include()
()from one phase are usually reviewed for completeness and accuracy and approved before work starts on the next phase.
() are individuals and organizations that are actively involved in the project, or whose interests may be affected as a result of project execution or project completion.
The()process analyzes the effect of risk events and assigns a numerical rating to those risks.
Project () Management includes the processes required to ensure that the project includes all the work required, and only the work required, to complete the project successfully.
() is one of the quality planning outputs.
In approximating costs, the estimator considers the possible causes of variation of the cost estimates, including() .
The()provides the project manager with the authority to apply organizational resources to project activities.