The()process analyzes the effect of risk events and assigns a numerical rating to those risks.
A.Risk Identification
B.Quantitative Risk Analysis
C.Qualitative Risk Analysis
D.Risk Monitoring and Control
您可能感興趣的試卷
你可能感興趣的試題
Project() Management is the Knowledge Area that employs the processes required to ensure timely and appropriate generation, collection, distribution, storage, retrieval, and ultimate disposition of project information.
A.Integration
B.Time
C.Planning
D.Communication
()is a category assigned to products or services having the same functional use but different technical characteristics. It is not same as quality.
A.Problem
B.Grade
C.Risk
D.Defect
Project Quality Management must address the management of the project and the() of the project. While Project Quality Management applies to all projects, regardless of the nature of their product, product quality measures and techniques are specific to the particular type of product produced by the project.
A.performance
B.process
C.product
D.object
In approximating costs, the estimator considers the possible causes of variation of the cost estimates, including() .
A.budget
B.plan
C.risk
D.contract
On some projects, especially ones of smaller scope, activity sequencing, activity resource estimating, activity duration estimating, and () are so tightly linked that they are viewed as a single process that can be performed by a person over a relatively short period of time.
A.time estimating
B.cost estimating
C.project planning
D.schedule development
Project () Management includes the processes required to ensure that the project includes all the work required, and only the work required, to complete the project successfully.
A.Integration
B.Scope
C.Configuration
D.Requirement
In the project management context,() includes characteristics of unification, consolidation, articulation, and integrative actions that are crucial to project completion, successfully meeting customer and other stakeholder requirements, and managing expectations.
A.Integration
B.Scope
C.Configuration
D.Requirement
Organizations perform work to achieve a set of objectives. Generally, work can be categorized as either projects or operations, although the two sometimes are()
A.confused
B.same
C.overlap
D.dissever
()from one phase are usually reviewed for completeness and accuracy and approved before work starts on the next phase.
A.Process
B.Milestone
C.Work
D.Deliverables
()involves comparing actual or planned project practices to those of other projects to generate ideas for improvement and to provide a basis by which to measure performance. These other projects can be within the performing organization or outside of it, and can be within the same or in another application area.
A.Metrics
B.Measurement
C.Benchmarking
D.Baseline
最新試題
Project() Management is the Knowledge Area that employs the processes required to ensure timely and appropriate generation, collection, distribution, storage, retrieval, and ultimate disposition of project information.
空白(1)處應(yīng)選擇()
()is the budgeted amount for the work actually completed on the schedule activity or WBS component during a given time period.
()from one phase are usually reviewed for completeness and accuracy and approved before work starts on the next phase.
The process of()schedule activity durations uses information on schedule activity scope of work, required resource types, estimated resource quantities, and resource calendars with resource availabilities.
Organizations perform work to achieve a set of objectives. Generally, work can be categorized as either projects or operations, although the two sometimes are()
On some projects, especially ones of smaller scope, activity sequencing, activity resource estimating, activity duration estimating, and () are so tightly linked that they are viewed as a single process that can be performed by a person over a relatively short period of time.
() is one of the quality planning outputs.
()involves comparing actual or planned project practices to those of other projects to generate ideas for improvement and to provide a basis by which to measure performance. These other projects can be within the performing organization or outside of it, and can be within the same or in another application area.
The ()Process Group consists of the processes used to complete the work defined in the project management plan to accomplish the project's requirements.