The()process analyzes the effect of risk events and assigns a numerical rating to those risks.

A.Risk Identification
B.Quantitative Risk Analysis
C.Qualitative Risk Analysis
D.Risk Monitoring and Control


你可能感興趣的試題

最新試題

Project() Management is the Knowledge Area that employs the processes required to ensure timely and appropriate generation, collection, distribution, storage, retrieval, and ultimate disposition of project information.

題型:單項選擇題

空白(1)處應(yīng)選擇()

題型:單項選擇題

()is the budgeted amount for the work actually completed on the schedule activity or WBS component during a given time period.

題型:單項選擇題

()from one phase are usually reviewed for completeness and accuracy and approved before work starts on the next phase.

題型:單項選擇題

The process of()schedule activity durations uses information on schedule activity scope of work, required resource types, estimated resource quantities, and resource calendars with resource availabilities.

題型:單項選擇題

Organizations perform work to achieve a set of objectives. Generally, work can be categorized as either projects or operations, although the two sometimes are()

題型:單項選擇題

On some projects, especially ones of smaller scope, activity sequencing, activity resource estimating, activity duration estimating, and () are so tightly linked that they are viewed as a single process that can be performed by a person over a relatively short period of time.

題型:單項選擇題

() is one of the quality planning outputs.

題型:單項選擇題

()involves comparing actual or planned project practices to those of other projects to generate ideas for improvement and to provide a basis by which to measure performance. These other projects can be within the performing organization or outside of it, and can be within the same or in another application area.

題型:單項選擇題

The ()Process Group consists of the processes used to complete the work defined in the project management plan to accomplish the project's requirements.