單項(xiàng)選擇題

 The()technique involves using project characteristics in a mathematical model to predict total project cost. Models can be simple or complex.

A.costaggregation
B.reserve analysis
C.parametricestimating
D.funding limit reconciliation


你可能感興趣的試題

1.單項(xiàng)選擇題

An example of scope verification is ().

A.review the performance ofan installed software module
B.managing changes to the project schedule
C.decomposing the WBS to a work package level
D.performing a benefit/cost analysis to determine if we should proceed with the project

2.單項(xiàng)選擇題

The connection between two networks from an intemet is handled by a machine known as a()

A.bridge
B.server
C.router
D.switch

3.單項(xiàng)選擇題

Creating WBS means subdividing the major project deliverables into smaller components until the deliverables are defined to the level()

A.independentresource
B.individualworkload
C.workmilestone
D.workpackage

4.單項(xiàng)選擇題

Contract closeout is a process that involves()

A.Customer satisfaction analysis and final payment
B.Administrative closeout and archiving records
C.Finial contractor payment and Lessons learned
D.Product verification and administrative closeout