()is a category assigned to products or services having the samefunctional use but different technical characteristics. Itisnotsameasquality.
A.Problem
B.Grade
C.Risk
D.Defect
您可能感興趣的試卷
- 2009年計算機技術與軟件專業(yè)技術資格高級信息系統(tǒng)項目管理師上半年上午試卷
- 2009年計算機技術與軟件專業(yè)技術資格高級信息系統(tǒng)項目管理師下半年上午試卷
- 2010年計算機技術與軟件專業(yè)技術資格高級信息系統(tǒng)項目管理師上半年上午試卷
- 2010年計算機技術與軟件專業(yè)技術資格高級信息系統(tǒng)項目管理師下半年上午試卷
- 2011年計算機技術與軟件專業(yè)技術資格高級信息系統(tǒng)項目管理師上半年上午試卷
- 2011年計算機技術與軟件專業(yè)技術資格高級信息系統(tǒng)項目管理師下半年上午試卷
- 2012年計算機技術與軟件專業(yè)技術資格高級信息系統(tǒng)項目管理師上半年上午試卷
你可能感興趣的試題
Project Quality Management must address the management of the project and the()ofthe project. While Project Quality Management applies to all projects,regardless of the nature of their product, product quality measures and techniques are specific to the particular type of product produced by the project.
A.performance
B.process
C.product
D.object
In approximating costs, the estimator considers the possible causes ofvariation of the cost estimates, including()
A.budget
B.plan
C.risk
D.contract
On some projects, especially ones of smaller scope, activity sequencing, activity resource estimating, activity duration estimating, and()are so tightly linkedthat they are viewed as a single process that can be performed by a person over a relatively short period of time.
A.time estimating
B.cost estimating
C.project planning
D.schedule development
Project()Management includes the processes required to ensure that theproj ect includes all the work required, and only the work required, to complete the project successfully.
A.Integration
B.Scope
C.Configuration
D.Requirement
In the project management context()includes characteristics of unification,consolidation, articulation, and integrative actions that are crucial to project completion,successfully meeting customer and other stakeholder requirements, and managing expectations.
A.integration
B.scope
C.process
D.charter
最新試題
The parties to government procurement refer to the principal entities of all kinds that enjoy rights and undertake obligations in government procurement, including the procuring entities, the ()and the procuring agencies.
Changes may be requested by any stakeholder involved with the project, but changes can be authorized only by()
空白(1)處填()
An activity has an early start date-of the lOth and a late start date of the 19th. The activity also has a duration of 4 days. There are no nonworkdays. From the information given, ()what can be concluded about the activity?
空白(1)處填()
A ()is a collection of projects and other work that are grouped together to facilitate effective management ofthat work to meet strategic business objectives.
空白(1)處填()
空白(3)處填()