單項選擇題In which case is the IOPP Certificate of an inspected vessel NOT invalidated? ()

A.The required oily-water separator malfunctions
B.The ship is transferred to Liberian registry
C.An annual survey is conducted fifteen months after the date of certificate issuance
D.A 15 ppm oily-water separator is replaced by a 100 ppm oily-water separator


您可能感興趣的試卷

你可能感興趣的試題

1.單項選擇題In setting the valves on a steam-smothering system on a tanker,the master control valve to cargo tanks should be().

A.open and individual tank valves open
B.open and the individual tank valves closed
C.closed and the individual tank valves closed
D.closed and the individual tank valves open

2.單項選擇題In order to reduce the accumulation of static electricity while loading petroleum products,you should().

A.start to load at maximum pressure
B.start to load slowly
C.increase the air flow into the tank
D.use the overall method of loading only

4.單項選擇題How must each storage tank for helicopter fuel on a ship be marked?()

A.DANGER - KEEP AWAY
B.DANGER - EXPLOSIVE VAPORS
C.DANGER - NO SMOKING
D.DANGER - FLAMMABLE LIQUID

5.單項選擇題If the Certificate of Inspection of a damaged tank barge has expired,which certificate may be issued to allow its movement to a repair facility? ()

A.Change of employment
B.Permit to proceed
C.Application for inspection
D.Temporary Certificate of Inspection

最新試題

Every oil tanker operating with dedicated clean ballast tanks shall be()with a Dedicated Clean Ballast Tank Operation Manual detailing the system and specifying operational procedures.

題型:單項選擇題

If you are bunkering and you close off one tank in the line of tanks being filled,the rate of flow to other open tanks on the same line will().

題型:單項選擇題

Chemical Tankers are generally referred to the cargo ships constructed or adapted and used for the carriage of().

題型:單項選擇題

In setting the valves on a steam-smothering system on a tanker,the master control valve to cargo tanks should be().

題型:單項選擇題

Every new crude oil tanker of 20000 tons deadweight and above and every new product carrier of 30000 tons deadweight and above shall be()with segregated ballast tanks.

題型:單項選擇題

For the purpose of()tank or hold washings from any vessel,an application shall be made to Harbor Authorities for approval.

題型:單項選擇題

In which case is the IOPP Certificate of an inspected vessel NOT invalidated? ()

題型:單項選擇題

In order to reduce the accumulation of static electricity while loading petroleum products,you should().

題型:單項選擇題

Every new crude oil tanker of 20000 tons deadweight and above and every new product carrier of 30000 tons deadweight and above shall be()with segregated ballast tanks.

題型:單項選擇題

Individual wires,used in systems greater than 50 volts,().

題型:單項選擇題