單項選擇題

()involves comparing actual or planned project practices to those of other projects to generate ideas for improvement and to provide a basis by which to measure performance. These other projects can be within the performing organization or outside of it, and can be within the same or in another application area.

A.Metrics
B.Measurement
C.Benchmarking
D.Baseline


你可能感興趣的試題

4.單項選擇題

The () describes, in detail, the project's deliverables and the work required to create those deliverables.

A.project scope statement
B.project requirement
C.project charter
D.product specification

5.單項選擇題The()provides the project manager with the authority to apply organizational resources to project activities.

A.project management plan
B.contract
C.project human resource plan
D.project charter

8.單項選擇題

The() defines the phases that connect the beginning of a project to its end.

A.schedule
B.project life cycle
C.temporary
D.milestone

9.單項選擇題

()means that every project has a definite beginning and a definite end.

A.Project phase
B.Unique
C.Temporary
D.Closure

10.單項選擇題

() is one of the quality planning outputs.

A.Scope base line
B.Cost of quality
C.Product specification
D.Quality checklist

最新試題

Which of the following statement related to PMO is not correct?()

題型:單項選擇題

PDM includes four types of dependencies or precedence relationships: (). The completion of the successor activity depends upon the initiation of the predecessor activity.

題型:單項選擇題

()means that every project has a definite beginning and a definite end.

題型:單項選擇題

In the project management context,() includes characteristics of unification, consolidation, articulation, and integrative actions that are crucial to project completion, successfully meeting customer and other stakeholder requirements, and managing expectations.

題型:單項選擇題

The () describes, in detail, the project's deliverables and the work required to create those deliverables.

題型:單項選擇題

() are individuals and organizations that are actively involved in the project, or whose interests may be affected as a result of project execution or project completion.

題型:單項選擇題

()is a category assigned to products or services having the same functional use but different technical characteristics. It is not same as quality.

題型:單項選擇題

On some projects, especially ones of smaller scope, activity sequencing, activity resource estimating, activity duration estimating, and () are so tightly linked that they are viewed as a single process that can be performed by a person over a relatively short period of time.

題型:單項選擇題

The inputs of developing project management plan do not include()

題型:單項選擇題

空白(1)處應(yīng)選擇()

題型:單項選擇題