單項(xiàng)選擇題

You are working on the cost budget for one project. Which of the following is true()

A.This process assigns cost estimates to project activities including risks and contingency plans.
B.The cost baseline will be used to measure variances and future project performance.
C.This process assigns cost estimates for expected future period operating costs.
D.The cost baseline is the expected cost for the project.


你可能感興趣的試題

1.單項(xiàng)選擇題An activity has an early start date-of the lOth and a late start date of the 19th. The activity also has a duration of 4 days. There are no nonworkdays. From the information given, ()what can be concluded about the activity?

A.Total float for the activity is 9 days.
B.The early finish date ofthe activity is the end ofthe day on the 14th.
C.The late finish date is the 25th.
D.The activity can be completed in 2 days ifthe resources devoted to it are doubled.

3.單項(xiàng)選擇題

Creating WBS means subdividing the major project deliverables into smaller components until the deliverables are defined to the level()

A.independentresource
B.individualworkload
C.workmilestone
D.workpackage

5.單項(xiàng)選擇題

Changes may be requested by any stakeholder involved with the project, but changes can be authorized only by()

A.executive IT manager
B.projectmanger
C.change control board
D.projectsponsor

最新試題

空白(3)處填()

題型:?jiǎn)雾?xiàng)選擇題

空白(3)處填()

題型:?jiǎn)雾?xiàng)選擇題

Your project is behind schedule due to conflict between team members . Havingresolved the conflict, to get the project back on schedule , you should consider ().

題型:?jiǎn)雾?xiàng)選擇題

The parties to government procurement refer to the principal entities of all kinds that enjoy rights and undertake obligations in government procurement, including the procuring entities, the ()and the procuring agencies.

題型:?jiǎn)雾?xiàng)選擇題

You are working on the cost budget for one project. Which of the following is true()

題型:?jiǎn)雾?xiàng)選擇題

In which form of projects origination would the project manager be likely to exercise the most control over Project resources.()

題型:?jiǎn)雾?xiàng)選擇題

空白(2)處填()

題型:?jiǎn)雾?xiàng)選擇題

There are strategies typically deal with threats or risk that may have negative impacts on project objectives if they occur, some other strategies are suggested to deal with risks with potentially positive impacts. ()is a risk response strategy that may be adopted for either threats or opportunities.

題型:?jiǎn)雾?xiàng)選擇題

Project selection methods involve measuring value or attractiveness to the project owner or sponsor and may include other organizational decision criteria ()is not a project selection method.

題型:?jiǎn)雾?xiàng)選擇題

The connection between two networks from an intemet is handled by a machine known as a()

題型:?jiǎn)雾?xiàng)選擇題