單項(xiàng)選擇題

In the process of communication requirement analysis, the project manager should consider the number of potential communication channels or paths as an indicator of the complexity of a project's communication. According to Metcalfe's Law, a project with 10 stakeholders has()potential communication channels.

A.10
B.45
C.50
D.100


你可能感興趣的試題

3.單項(xiàng)選擇題

Contract closeout is a process that involves()

A.Customer satisfaction analysis and final payment
B.Administrative closeout and archiving records
C.Finial contractor payment and Lessons learned
D.Product verification and administrative closeout

4.單項(xiàng)選擇題

In which form of projects origination would the project manager be likely to exercise the most control over Project resources.()

A.Strongmatrix
B.Projectized
C.Projectcoordinator
D.Weakmatrix

5.單項(xiàng)選擇題

You are working on the cost budget for one project. Which of the following is true()

A.This process assigns cost estimates to project activities including risks and contingency plans.
B.The cost baseline will be used to measure variances and future project performance.
C.This process assigns cost estimates for expected future period operating costs.
D.The cost baseline is the expected cost for the project.