單項(xiàng)選擇題

The ()Process Group consists of the processes used to complete the work defined in the project management plan to accomplish the project's requirements.

A.Planning
B.Executing
C.Monitoring and Controlling
D.Closing


你可能感興趣的試題

2.單項(xiàng)選擇題

The() defines the phases that connect the beginning of a project to its end.

A.schedule
B.project life cycle
C.temporary
D.milestone

3.單項(xiàng)選擇題

()means that every project has a definite beginning and a definite end.

A.Project phase
B.Unique
C.Temporary
D.Closure

4.單項(xiàng)選擇題

() is one of the quality planning outputs.

A.Scope base line
B.Cost of quality
C.Product specification
D.Quality checklist

5.單項(xiàng)選擇題

The inputs of developing project management plan do not include()

A.project charter
B.stakeholder management strategy
C.project scope statement
D.outputs from planning processes

6.單項(xiàng)選擇題

Which of the following statement related to PMO is not correct?()

A.The specific form, function, and structure of a PMO are dependent upon the needs of the organization that it supports.
B.One of the key features of a PMO is managing shared resources across all projects administered by the PMO.
C.The PMO focuses on the specified project objectives.
D.The PMO optimizes the use of shared organizational resources across all projects.

最新試題

The()process analyzes the effect of risk events and assigns a numerical rating to those risks.

題型:?jiǎn)雾?xiàng)選擇題

Organizations perform work to achieve a set of objectives. Generally, work can be categorized as either projects or operations, although the two sometimes are()

題型:?jiǎn)雾?xiàng)選擇題

The () describes, in detail, the project's deliverables and the work required to create those deliverables.

題型:?jiǎn)雾?xiàng)選擇題

Which of the following statement related to PMO is not correct?()

題型:?jiǎn)雾?xiàng)選擇題

In the project management context,() includes characteristics of unification, consolidation, articulation, and integrative actions that are crucial to project completion, successfully meeting customer and other stakeholder requirements, and managing expectations.

題型:?jiǎn)雾?xiàng)選擇題

The()provides the project manager with the authority to apply organizational resources to project activities.

題型:?jiǎn)雾?xiàng)選擇題

PDM includes four types of dependencies or precedence relationships: (). The completion of the successor activity depends upon the initiation of the predecessor activity.

題型:?jiǎn)雾?xiàng)選擇題

()is a category assigned to products or services having the same functional use but different technical characteristics. It is not same as quality.

題型:?jiǎn)雾?xiàng)選擇題

()involves comparing actual or planned project practices to those of other projects to generate ideas for improvement and to provide a basis by which to measure performance. These other projects can be within the performing organization or outside of it, and can be within the same or in another application area.

題型:?jiǎn)雾?xiàng)選擇題

()from one phase are usually reviewed for completeness and accuracy and approved before work starts on the next phase.

題型:?jiǎn)雾?xiàng)選擇題